(1)各司其责(R&R): 你干的是班长的活,就不要操军长的心。你的责任没那么大。
(2)时间管理(time management):
Network change and software testing after the change are sequential events (finish-to-start relationship).
Time to finish testing = X (network change completion milestone) + Y (time needed to test in new env.)
Bottom line:
It is a problem. However, you are not the cause. You are the symptom. Do help resolve the problem. Don't lose sleep over it. You are not responsible for other people's delays and poor planning.