这种压力常见。从PM的角度说两点。。。

来源: 2012-02-02 17:26:32 [博客] [旧帖] [给我悄悄话] 本文已被阅读:

(1)各司其责(R&R): 你干的是班长的活,就不要操军长的心。你的责任没那么大。

(2)时间管理(time management):

Network change and software testing after the change are sequential events (finish-to-start relationship).

Time to finish testing = X (network change completion milestone) + Y (time needed to test in new env.)

Bottom line:

It is a problem. However, you are not the cause. You are the symptom. Do help resolve the problem. Don't lose sleep over it. You are not responsible for other people's delays and poor planning.