1. We were supposed to move the furnace into the attic so the se

回答: 两个问题请教波老师:3apples2015-02-12 14:11:17

get heat directly. He looked at the space under the (unfinished)attic floor.

2. Drill holes every 16 in around the house and rent a machine from HD. Pump in fire proofed shredded newspaper until filled the space between vertical beams, then move on to the next hole.

所有跟帖: 

i see. thanks. how much does it cost (material and labor )? of -3apples- 给 3apples 发送悄悄话 (0 bytes) () 02/12/2015 postreply 14:17:40

if labor is 200-300 per day, it could be about $1250-1750.估计我人工算 -3apples- 给 3apples 发送悄悄话 (118 bytes) () 02/12/2015 postreply 14:24:24

Well, you save hundreds of heating bill every year. -borisg- 给 borisg 发送悄悄话 borisg 的博客首页 (0 bytes) () 02/12/2015 postreply 14:26:27

是的,投资不大,但是很值得。 -3apples- 给 3apples 发送悄悄话 (0 bytes) () 02/12/2015 postreply 14:51:50