Are the quotes too high or reasonable? I was offered 2000 dollar off if I use them. ($19xxx.xx for goodman and $21xxx.xx for lennox)
Replace old AC/Furnance with heat pump, replace old duct with new duct system
Goodman or Lennox? 自住房
Details:
Equipment options 1
Goodman GZV6SA6010 5-ton variable capacity inverter outdoor
heat pump Goodman AHVE60DP0300 5-ton indoor air handler with electronically controlled motor
Daikin One thermostat with Wi-Fi and phone app
Labor: $9,729.00
Equipment And MATERIAL: $13,992.00
TOTAL PRICE ON ABOVE: $23,721.00
Permit, Acquisition Fee and Inspections: $535.78
3rd Party Hers Testing – Ca Title 24: $475.00
Sales Tax: $1,364.22
TOTAL PROJECT: $26,096.00
Rebate: $5,250.00
NET PROJECT COST: $21,230.00
Option 2
Lennox 16.8 SEER2 :
Lennox EL18KSLV-060-230 5-ton variable capacity inverter outdoor heat pump
Lennox CBK45UHET-060-71 5-ton indoor air handler with electronically controlled motor
Honeywell Focus Pro S200 Thermostat with Wi-Fi and phone app
Labor: $10,119.00
Equipment And MATERIAL: $15,768.00
TOTAL PRICE ON ABOVE: $25,887.00
Permit, Acquisition Fee and Inspections: $535.62
3rd Party Hers Testing – Ca Title 24: $475.00
Sales Tax: $1,537.38
TOTAL PROJECT: $28,435.00
Rebate:$5,250.00
NET PROJECT COST: $23,185.00
Detailed work?
WE PROPOSED TO FURNISH MATERIALS AND LABOR FOR INSTALLATION OF A SPLIT HEATING AND AIR CONDITIONING SYSTEM INCLUDING ATTIC DUCT WORK REPLACEMENT ACCORDING TO THE FOLLOWING SPECIFICATIONS:
Work includes: Remove existing equipment and related materials from job site
Relocate outdoor unit to behind chimney
Seal existing return air cavity Merv 13 media air cleaner
Sheet metal Connections to existing refrigerant lines
Connections to existing condensate drain line system with new safety shut off
Provide external condensate pan with shut off
Eliminate secondary condensate drain line and remove related gutter
Connections to existing low voltage control
wiring New 230v electrical circuit to air handler
Refrigerant system evacuation to below 500 microns with vacuum pump
Precise refrigerant charge using digital gauges
Materials
Labor
Duct Replacement:
Perform computerized room by room heat load calculations with air flow requirements using ACCA Manual J method
Design new duct system and plans using ACCA Manual D method
Install new duct system using UL listed class 1 flex duct to existing supply air outlets and return air inlets. Install manual volume dampers in all final duct lines
Seal all metal-to-metal joints with duct mastic Insulate all exposed sheet metal with 1.5” fiberglass insulation Seal duct system to meet California Title 24 leakage requirements
New bar type return air filter grill
Materials
Labor