Day 183, in the event of this catastrophe fire loss....

Day 183, in the event of this catastrophe fire loss....

today, marks the 6 months anniversary of the fire lost...

we had passed all mechanical and drywall inspections, into the painting phase...

after 18 5-gal buckets of primer, we finished priming all the drywalls, next we will paint up-stair first, then trimming and cabinets, after that we begin to work on the down stair units.

the snow and ice this week, has delayed us few days... 

所有跟帖: 

When you will start sheetrock? -RE8888- 给 RE8888 发送悄悄话 RE8888 的博客首页 (0 bytes) () 12/17/2010 postreply 11:50:04

drywalls already up, we painting now -jy101- 给 jy101 发送悄悄话 jy101 的博客首页 (0 bytes) () 12/17/2010 postreply 12:22:14

Then, your building will be ready in 5~6 weeks. -RE8888- 给 RE8888 发送悄悄话 RE8888 的博客首页 (27 bytes) () 12/17/2010 postreply 16:36:41

So, it should fill up before March? Sounds great. -sunskitehomes- 给 sunskitehomes 发送悄悄话 sunskitehomes 的博客首页 (0 bytes) () 12/17/2010 postreply 12:05:26

i am hoping we done on 2nd week of Feb, -jy101- 给 jy101 发送悄悄话 jy101 的博客首页 (128 bytes) () 12/17/2010 postreply 12:27:09