Day 105, in the event of this catastrophe fire loss....
finally, the truss is set, roof will be done tomorrow.
electrician and plumber will start later this week, we should be complete the mechanical phase with 4 weeks.
getting a bid for insulation and siding now.
Day 105, in the event of this catastrophe fire loss....
所有跟帖:
•
show us some pictures if you have please
-flying_bird-
♀
(0 bytes)
()
09/28/2010 postreply
06:10:27
•
haha, don't know how to post pics...
-jy101-
♂
(0 bytes)
()
09/28/2010 postreply
10:39:36
•
How to post picture? This is the link.
-SunshineInCA-
♀
(43 bytes)
()
09/28/2010 postreply
12:57:09
•
Thanks for sharing your experience
-sunskitehomes-
♂
(51 bytes)
()
09/28/2010 postreply
07:44:32
•
请问你建造期间的租金损失是否包括在保险费补赏当中?谢!
-万枫-
♂
(0 bytes)
()
09/28/2010 postreply
07:54:44
•
if your insurance policy including lost of income rider...
-jy101-
♂
(390 bytes)
()
09/28/2010 postreply
10:43:45
•
That is great! Thanks for sharing!
-万枫-
♂
(0 bytes)
()
09/28/2010 postreply
12:07:15