谢谢大家!沟通没有成功,contractor 说下周一找律师 file lien

来源: 2019-09-13 15:51:40 [旧帖] [给我悄悄话] 本文已被阅读:

我回复他说:As I have conveyed to you several times, I had no intention not to pay the bill. My request is really simple: bill the invoice based on the actual labor on the project. If you file the lien, the county clerk’s office would require the itemized statement about labor and materials.

他回复:That's not true. It was a bid. The bid stands and the work is done.

这大概就是柠檬说的 ”bound"吧.  教训啊。

我给county clerk office 打电话,他们说contrator 有一年的时间来perfect the lien. 轻微大家,如果上法庭的话,我的worst scenario 会是什么?如果严重的话,我就付钱了事,就当买教训好了。